Right now the Daytona Beach Boardwalk runs from the north end of the Ocean Walk Resort to the southern end of Breakers Oceanfront Park, as the Daytona Beach News-Journal described it in May. South of the park the pavers stop. Near the pier, the city owns a vacant parcel at 29 S. Ocean Ave. that it paid more than $2 million for.
Extending the walkway and finding something to put next to it work as one plan on this stretch of beachside. The city bought land, is building the walkway out from Breakers Oceanfront Park toward Harvey Avenue, and is now looking for a reason for people to walk it. Over the past 17 months, the city's stated idea for that reason has changed.
The city bought the land before the seawall went in
In June 2025, the Daytona Beach Community Redevelopment Agency voted to spend up to $2.2 million, plus about $15,000 in closing costs, from Main Street CRA tax-increment funds to buy the vacant parcel at 29 South Ocean Avenue. Citizen Portal's summary of that meeting said the purchase was meant to support the city's Boardwalk and redevelopment plans. The city's 2024–25 CRA annual report lists "29 South Ocean" among the Main Street CRA's land acquisitions and records $2,186,350.48 spent on land acquisition in 2025.
That order of events matters for anyone who walks this part of the beach. When WKMG ClickOrlando covered the city's $2.2 million beachfront purchase that month, it reported that one of the main reasons for buying was to kickstart the plan to extend the Boardwalk down to Harvey Avenue. Design and permitting work on the extension had begun a month earlier, in May 2025, but the seawall construction came after the purchase. The walkway is part of how the city plans to make that land worth visiting.
The plan for that land has moved from a hotel to rides
In the same June 2025 report, ClickOrlando said the city hoped to bring a boutique hotel or similar business to the land, which sat next to the future site of Señor Frog's. City Commissioner Ken Strickland described the gap this way at the time:
"We don't have rides up by the Boardwalk anymore; it stops right there at the pier, so we need to do something to create some change."
By fall 2026, the city was asking for something different. On Sept. 22, it released RFP 2654RFP, seeking a consultant to help find and recruit "amusement park, and entertainment venue developers/operators." The proposal deadline was Oct. 27 at 2 p.m. on the city's procurement portal. Mayor Derrick Henry announced the search on Sept. 27, according to the News-Journal. The paper reported that city staff were seeking companies interested in helping identify "amusement park, theme attraction, entertainment, hospitality and tourism operators interested in investing in Daytona Beach."
ClickOrlando's Oct. 1 report put the effort on the nearly one-acre, city-owned property at 29 S. Ocean Ave., close to the Boardwalk, the Daytona Beach Pier, hotels and restaurants. Ideas the city listed include amusement rides, entertainment venues, food truck parks and event spaces. Whatever concept moves forward needs City Commission approval. The station noted that Daytona Beach has lost classic rides over the years, including the Ferris wheel, the bumper cars and the Tilt-A-Whirl. Strickland's wish list was specific:
"I'd like to see a Ferris wheel and some little spin-around things. Tilt-A-Whirl or something along those lines."
He also said private property owners are welcome to add amusement rides on their own land. The RFP doesn't pick an operator. It hires the consultant who will go find one, and the procurement Q&A says the city set no budget range, asking firms to propose fees based on their approach.
The walkway money came through by one vote
The extension has already started, at least below ground. In May 2026, ClickOrlando reported that crews were building a seawall set into the sand to serve as the foundation, while the Boardwalk itself was still in design. By October, the plan was an ADA-compliant walkway with beach access, lighting and railings, built with pavers and concrete to match the existing Boardwalk, connecting Breakers Oceanfront Park to a beach entrance near Harvey Avenue.
Paying for it was the close call. The city applied for a $400,000 Volusia County ECHO grant and lined up a $400,000 match from the Main Street CRA. The ECHO Board did not support the application at its August review. The Volusia County Council approved its 2026 ECHO awards on Oct. 6 as staff recommended, except for the Daytona proposal, which got a separate vote. The council's action list shows the Harvey Avenue Boardwalk Extension and Beach Access Improvement project passed 4 to 3 on a motion by Reinhart, seconded by Santiago, with Robins, Johansson and Kent opposed.
Hometown News Volusia reported that ECHO grants require a dollar-for-dollar match and that recipients have two years to finish their projects. The same round funded other projects Daytona Beach residents will recognize, including $2.5 million for event-lawn and walking-path amenities at the Museum of Arts & Sciences' Brown site next to the Tuscawilla Preserve.
Here is the sequence so far:
| When | What happened | Who acted |
|---|---|---|
| May 2025 | Engineering, design, surveying and permitting begin for the extension | City of Daytona Beach and its consultant |
| June 2025 | Up to $2.2 million authorized to buy 29 S. Ocean Ave. | Daytona Beach CRA |
| May 2026 | Seawall foundation work reported underway | City contractor crews |
| August 2026 | ECHO grant application not supported | ECHO advisory board |
| Sept. 22, 2026 | RFP 2654RFP released to recruit an amusement consultant | City of Daytona Beach |
| Oct. 6, 2026 | $400,000 ECHO grant approved, 4 to 3 | Volusia County Council |
| Oct. 27, 2026 | Consultant proposals due | City procurement |
The businesses already there asked for this
For years, the businesses on the south end of the Boardwalk have been asking for exactly this kind of change. Dino Paspalakis, whose family has owned the Mardi Gras Arcade since the 1950s, told ClickOrlando in June 2025 that the family was remodeling the outside of both Pizza King and the Mardi Gras. He said business owners had been asking the city for improvements that would bring visitors back. At the time, he pointed to Saturday-night fireworks and the Friends of the Bandshell concerts as the draws that were already there.
By May 2026, the requests were more specific. Kenneth Morris at the Mardi Gras arcade told ClickOrlando in its May 2026 report, "I would like the city to build next door to us fun centers for the families that do come down here." Owners in the same report pointed to a big, empty lot just north of the pier as the place for family attractions. Louie Louizes, owner of Ocean Ave Gallery, wanted the spending to go toward the Boardwalk that already exists before it goes south. "You got to make the one you got already work," he said.
When the 2025 hotel idea became the 2026 call for rides, the city's plan moved toward what these owners had been asking for. The fall 2026 version of the plan adds both things the owners wanted, more walkway and more to do next to it.
What has to happen before anyone walks it
All of this is still in early steps. Here's what has to happen next, as of the city's October update:
- State and federal permits. Applications for the extension are with the Florida Department of Environmental Protection and the U.S. Army Corps of Engineers, and the city and its consultant are answering requests for more information.
- Walkway construction. If funding and permits are in place, construction is expected to begin in 2027 and finish in 2028.
- Harvey Avenue tie-in. The city is coordinating with Volusia County on planned beach-access improvements at Harvey Avenue, and with nearby development, so the pieces connect.
- A consultant, then an operator, then a vote. The consultant from RFP 2654RFP will recruit operators, and any concept for 29 S. Ocean Ave. goes to the City Commission for approval.
The two-year ECHO completion window runs alongside that construction schedule, so the grant and the 2028 target are tied together. City Commission agendas are the next place the 29 S. Ocean Ave. plan will show up in public, because no concept for the lot moves forward without a vote there.
I've spent more than 40 years watching this beachside change, and few pieces of land matter as much to it as the empty acre by the pier. If you own near the Boardwalk and want to talk through what a walkway extension and a possible new attraction could mean for your property's value, Stacy Kelly is glad to put together a free home valuation built on this part of Daytona Beach.